Data

Date:
07-12-1998
Country:
USA
Number:
98-1165-B
Court:
United States District Court, S.D. California
Parties:
Ministry of Defense and Support for the Armed Forces of the Islamic Republic of Iran v. Cubic Defense Systems, Inc.

Keywords

STATE CONTRACTS - CONTRACT FOR THE SUPPLY AND INSTALLATION OF MILITARY EQUIPMENT - BETWEEN A UNITED STATES CORPORATION AND THE IRANIAN AIR FORCE

REFERENCE BY ARBITRAL TRIBUNAL TO THE UNIDROIT PRINCIPLES AS A SOURCE OF GENERAL PRINCIPLES OF LAW AND TRADE USAGES WITHOUT EXPRESS AUTHORIZATION BY PARTIES DOES NOT VIOLATE ARTICLE V (1) (C) OF THE 1958 NEW YORK CONVENTION

Abstract

On 25 June 1998, a petition was filed for an order confirming the ICC Award N° 7365/FMS of 5 May 1997 (see UNILEX UNIDROIT Principles, C.1997-5). In its counter-motion requesting the Court to refuse confirmation, the Respondent contended that the award dealt "with a difference not contemplated by or not falling within the terms of the submission to arbitration" and contained "decisions on matters beyond the scope of the submission to arbitration", thereby violating Article V(1)(c) of the 1958 New York Convention on the Recognition and Enforcement of Foreign Arbitration Awards, claiming that the Arbitral Tribunal exceeded the terms of the submission to arbitration in two respects: first, by issuing a ruling based upon legal theories not contemplated by and/or asserted by the parties; secondly by referring to the UNIDROIT Principles and to other international principles such as good faith and fair dealing, even though they were not indicated in the Terms of Reference as the applicable law.

The Court rejected both objections. As to the first one, the Court held that, because the ICC Award resolved the parties' claims arising from the contracts for the sale and installation of the sophisticated military equipment entered into by the parties, the fact that it was not based on the same legal theories as stated in the pleadings could not be a basis for refusing to confirm it. As to the Respondent's complaint concerning the application of the UNIDROIT Principles, according to the Court, "The Tribunal's reference to and application of the UNIDROIT Principles and principles such as good faith and fair dealing do not violate Article V(1)(c). The Tribunal applied these principles to differences contemplated by and falling within the terms of the submission to arbitration and therefore the Award does not violate Article V(1)(c)".

Fulltext

[...]

[1][2] The Court is asked to confirm the ICC Award pursuant to the United Nations Convention on the Recognition and Enforcement of Foreign Arbitration Awards ("Convention"), opened for signature June 10, 1958, 21 U.S.T. 2517, 330 U.N.T.S. 3, reprinted in 9 U.S.C. §§ 201-208. The United States became a party to the Convention in 1970, and Congress soon after enacted legislation implementing the provisions of the Convention into domestic law, codified as Chapter II of the Federal Arbitration Act ("FAA"), Pub.L. 91-368, 84 Stat. 692 (1970) (codified at 9 U.S.C. §§ 201-208). A district court's "review of a foreign arbitration award is quite circumscribed." Ministry of Defense of the Islamic Republic of Iran v. Gould, Inc., 969 F.2d 764, 770 (9th Cir.1992). There is a general pro-enforcement bias under the Convention. See Id.; see also Scherk v. Alberto-Culver Co., 417 U.S. 506, 519-20 & n. 15, 94 S. Ct. 2449, 41 L.Ed.2d 270 (1974). Upon application for an order confirming the award, the "district court has little discretion: 'The court shall confirm the award unless it finds one of the grounds for refusal or deferral of recognition or enforcement of the award specified in the said Convention.' " Ministry of Defense, 969 F.2d at 770 (citing 9 U.S.C. § 207).

[3] The grounds for refusing to recognize or enforce an arbitral award include:
(a) The parties to the agreement ... were, under the law applicable to them, under some incapacity, or the said agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law of the country where the award was made; or
(b) The party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or the arbitration proceedings or was otherwise unable to present [his or her] case; or
(c) The award deals with a difference not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration, provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, that part of the award which contain decisions on matters submitted to arbitration may be recognized and enforced;.... [FN2]

FN2. Article V(1)(d)-(e) and Article V(2) of the Convention also set forth grounds upon which a court may refuse to recognize or enforce a foreign arbitral award. Cubic, however, does not make claims pursuant to these provisions of the Convention and therefore these grounds are not before this Court.
Convention, art. V(1). In particular, courts should narrowly construe Article V(1)(c) in accordance with the Convention's general pro-enforcement bias. See Ministry of Defense, 969 F.2d at 770.
[4] Section 10 of the FAA and case law addressing domestic arbitration set forth grounds upon which a court may refuse to confirm an arbitration award. These grounds, however, are not applicable to confirmation under the Convention. The statute implementing the Convention states that a "court shall confirm the award unless it finds one of the grounds for refusal ... specified in the said Convention." 9 U.S.C. § 207. Thus, other provisions regarding arbitration are not applicable to petitions requesting confirmation of an arbitration award under the Convention. See Ministry of Defense, 969 F.2d at 770 (limiting discretion of district court to grounds to refusal specified in the Convention); Management & Technical Consultants S.A. v. Parsons-Jurden Int'l Corp., 820 F.2d 1531, 1533-34 (9th Cir.1987) ("Under the Convention, an arbiter's award can be vacated only on the grounds specified in the Convention."); see also Industrial Risk Insurers v. M.A.N. Gutehoffnungshutte GmbH, 141 F.3d 1434, 1446 (11th Cir.1998) (finding that "the Convention's enumeration of defenses is exclusive"); Yusuf Ahmed Alghanim & Sons, W.L.L. v. Toys "R" Us, Inc., 126 F.3d 15, 20 (2d Cir.1997) ("[T]he grounds for relief enumerated in Article V of the Convention are the only grounds available for setting aside an arbitral award."); M & C Corp. v. Erwin Behr GmbH & Co., 87 F.3d 844, 851 (6th Cir.1996) ("Article V of the Convention lists the exclusive grounds justifying refusal to recognize an arbitral award.").

B. Cubic's Opposition to Confirmation of the Arbitration Award

1. Article V(1)(c)
Cubic first contends that the ICC Award violates Article V(1)(c) of the Convention because it "deals with a difference not contemplated by or not falling within the terms of the submission to arbitration" and it "contains decisions on matters beyond the scope of the submission to arbitration." [FN3] Cubic also alleges that the award violates Article V(1)(c) because it ignores the terms of the Parties' Contracts. Thus, Cubic argues that the "Terms of Reference constitute the jurisdictional mandate of an arbitral panel, and any decision which exceeds the scope of that jurisdictional reference is improper."

FN3. Cubic also contends that the Award violates 9 U.S.C. § 10 of the FAA. As explained by this Court, § 10 of the FAA does not apply to claims brought under the Convention.

[5] Specifically, Cubic argues that the Tribunal decided issues not submitted by the Parties and issued a ruling based upon legal theories not contemplated by and/or asserted by the Parties. The legal theories and conclusions Cubic takes issue with are: (1) the "conclusion that the Parties agreed in 1979 to discontinue the Contracts at least for the time being, i.e., until the results of Cubic's attempt to resell the System would be known" (Award § 10.11); (2) the conclusion that there was "an implicit agreement for the postponement of the maturity date of any such claims until Cubic had resold the equipment or declared its inability to resell" (Procedural Order No. 6 § 1.3); (3) the conclusion that there was "a factual termination of the Contracts at the request of Iran" (Award § 11.22); and, (4) the finding that it can be implied from the Termination for Convenience Clause that "Cubic shall credit Iran with ... products manufactured for Iran prior to the termination of the Contracts." (Award § 13.6).
Cubic's objections are misguided. First, the Terms of Reference allow the Arbitrators leeway in resolving the conflict that the Parties presented to them. Cubic cites specific questions framed by the Terms of Reference and claims that the ICC Award's deviations from those particular questions constitutes a deviation from the Terms. However, as Iran points out, the questions posed for the Arbitrators were presented in the following manner in the Terms of Reference:
The issues to be determined shall be those resulting from the Parties' submissions and which are relevant to the adjudication of the Parties' respective claims and defenses. In particular, the Arbitral Tribunal may have to consider the following issues (but not necessarily all of these or only these, and not necessarily in the following order)....
(Terms of Reference § 4) (emphasis added). The Terms of Reference then proceed to list twelve issues that may be considered in the adjudication of the Parties' claims and defenses. The Arbitrators were not, however, explicitly required to consider all of these issues in resolving this contractual dispute. The Arbitrators were also not limited to the issues listed, but could consider additional issues in resolving this dispute. Furthermore, the Award is within the parameters of those twelve issues, even if the legal theories applied are different from those presented in the Parties' pleadings. Thus, based only on an evaluation of the Terms of Reference, the use of legal theories not presented by the Parties is acceptable under the Terms of Reference.

[6] Second, Cubic's claim that the use of legal theories not presented by the Parties precludes confirmation of the Award was rejected by the Ninth Circuit. See Ministry of Defense, 969 F.2d at 771. Under the Convention, a court is to determine "whether the award exceeds the scope of the [arbitration agreement], not whether the award exceeds the scope of the parties' pleadings." Id. Respondents in Ministry of Defense objected to confirmation of that award "because the award [was] not based on the same legal theory as that stated in the pleadings." The court found that the subject matter of respondent's claim was "obvious[ly]" the contracts between the parties and to the extent the "award resolves the claims and counterclaims connected with the two contracts it ... does not exceed the scope of the submission to arbitration." Id. Comparing Ministry of Defense to this case, the Court finds that the subject matter of this dispute is the Service and Sales Contracts between Cubic and Iran. The ICC Award resolves the Parties' claims arising from these Contracts and the fact that the Award is not based on the same legal theories as stated in the pleadings cannot be a basis for refusing to confirm it.

[7] Cubic also disputes the Tribunal's reference to the Principles of International Commercial Contracts published in 1994 by the Unidroit Institute ("UNIDROIT Principles") and the Tribunal's references to principles of fairness such as good faith and fair dealing. Cubic claims that reference to such international and equitable principles also violates Article V(1)(c) because this law exceeds the scope of the Terms of Reference. The reference to the UNIDROIT Principles does not exceed the scope of the Terms of Reference. One of the issues presented to the Tribunal was whether general principles of international law apply to this dispute. That Cubic disagrees with the Tribunal's response to the question posed by the Parties is not a reason to find that the Tribunal addressed issues beyond the scope of the Terms of Reference. The same is true for Cubic's assertions with regard to the Tribunal's references to equitable principles of contract law. [FN4]
FN4. Cubic relies on Beacon Journal Publ'g v. Akron Newspaper Guild, 114 F.3d 596, 600 (6th Cir.1997), for its contention that arbitration awards based on fairness and equity instead of the terms of the agreement should be overturned. Even if this case were binding on this Court, the case resolves a domestic arbitration dispute arising from a collective bargaining agreement and is therefore not applicable to the confirmation of arbitral awards under the Convention. See Ministry of Defense, 969 F.2d at 770; see also M & C Corp., 87 F.3d at 851 (6th Cir.1996).
As stated earlier, this Court's discretion in reviewing a foreign arbitration award is quite circumscribed. See Ministry of Defense, 969 F.2d at 770. The Tribunal's reference to and application of the UNIDROIT Principles and principles such as good faith and fair dealing do not violate Article V(1)(c). The Tribunal applied these principles to differences contemplated by and falling within the terms of the submission to arbitration and therefore the Award does not violate Article V(1)(c).

2. Article V(1)(a)

[8] Article V(1)(a) provides that a court may refuse to confirm an arbitral award if an agreement in writing, including an arbitral clause in a contract or an arbitration agreement, is not valid under the law to which the parties have subjected it. Cubic appears to be arguing that the four theories of the Tribunal that Cubic contests constitute oral amendments to the Contracts' arbitration clauses and the Terms of Reference. Cubic contends that these oral amendments violate the Convention's requirement that the agreements be in writing. Cubic's construction of the Award and the Convention is strained.
The arbitration clause in the Contracts and the Terms of Reference validly present the Tribunal with the task of resolving the dispute over the Contracts between Iran and Cubic resulting from the unusual circumstances surrounding the 1979 Iranian Revolution. This Court cannot refuse to confirm the Award simply because the legal theories and conclusions presented in the Award differ from those contemplated by the Parties in their pleadings. Legal theories used by adjudicators to resolve contract disputes are not considered oral amendments to the contract or the arbitration agreement. Article V(1)(a) of the Convention does not present this Court with grounds for refusing to confirm the Award.

3. Article V(1)(b)
[9] Article V(1)(b) allows a court to refuse confirmation of an arbitral award if the "party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or of the arbitration proceedings or was otherwise unable to present [his or her] case." Cubic contends that it was "denied a meaningful opportunity to present its case" because: (1) Iran shifted its factual and legal theories throughout the proceedings; (2) the Tribunal issued interim decisions regarding bifurcation of the proceedings; and (3) the legal theories and remedies articulated in the Award were not previously presented. Even if these allegations were true, these claims do not rise to the level required by Article V(1)(b) to justify a refusal by this Court to confirm the Award. Cubic's active participation in the entire process demonstrates notification of the proceedings, therefore Cubic presumably relies on the latter part of Article V(1)(b) to justify its claim. However, Cubic was also "otherwise able to present [its] case." Two hearings were held. Cubic also had several opportunities for briefing. Cubic had its "day in court" and had ample opportunity to present its interpretation of the facts and its legal theories to the Tribunal. Therefore, the Award does not violate Article V(1)(b).

III. CONCLUSION

The Court hereby GRANTS Iran's Petition for Confirmation of the Foreign Arbitral Award and, subsequently, the Court hereby DENIES Cubic's Cross-Motion to Vacate the May 5, 1997 ICC Arbitration Award.

IT IS SO ORDERED.}}

Source

Sources:
- 29 Fed. Suppl. 2nd, 1168
- Uniform Law Review / Revue de droit uniforme, 1999, 799

Commented on by:
- Prof. M.J. Bonell, Unidroit Principles: a significant recognition by a United States District Court, Unif. L. Rev. / Rev. dr. unif. 1999, 651

Abstract published in English and French:
- Uniform Law Review / Revue de droit uniforme, 1999, 1016-1017}}