Data
- Date:
- 07-11-2011
- Country:
- USA
- Number:
- 10-80851
- Court:
- U.S. District Court, Southern District of Florida
- Parties:
- Al Hewar Environmental & Public Health Establishment v. Southeast Ranch, LLC and Joel Gutierre
Keywords
RECOVERABLE DAMAGES - EQUAL TO THE LOSS FORESEEABLE BY THE PARTY IN BREACH (ART. 74)
Abstract
A buyer from the United Arab Emirates (U.A.E.) and an U.S. seller concluded a contract for the sale of a certain amount of compressed hay, to be supplied to the government of Abu Dhabi. The buyer paid a down payment to the seller. Subsequently, the buyer concluded a resale contract with the government of Abu Dhabi and the latter, as contractual guarantee, required the buyer to procure a performance bond. As the seller failed to deliver the goods, the buyer terminated the resale contract. Consequently, the government of Abu Dhabi not only refused to release the performance bond, but also severed its business relationship with the buyer. As a result, the buyer brought an action against the seller requesting damages arising out of the latter’s breach of contract.
As to the applicable law, the Court held that CISG governed the case since both parties had their places of business in different Contracting States (Art. 1(1)(a) CISG).
As to the merits, the Court ruled in favor of the buyer. By applying the criterion of foreseebility established in Art. 74 CISG with respect to the damages a party may be awarded in case of the other party's breach of contract, the Court held that the buyer was entitled to be paid the difference between the lost proceeds of the resale to Abu Dhabi's government and the remaining purchase price it was not obliged to pay on account of the seller’s non-performance. On the same ground, the Court acknowledged the buyer’s right to be compensated for the loss of the performance bond.
Fulltext
OPINION
THIS CASE involves a contract for the sale of hay between Al Hewar Environmental and Public Health Establishment ("Buyer"), the Plaintiff, and Southeast Ranch, LLC ("Seller"), along with its principals Joel Gutierrez and Dagmara Cabrera, the Defendants. Cabrera was voluntarily dismissed from the action and the remaining Defendants were defaulted as to liability for failure to respond to the Complaint on April 14, 2011. Order Granting in Part Pl.'s Mot. for Default J. [DE # 27]. The Court then held an evidentiary hearing regarding damages on October 11, 2011. Pursuant to 52(a), the Court sets forth its findings of fact and conclusions of law below.
I. Findings of Fact
A. Background
1. [Buyer] is a United Arab Emirates ("U.A.E.") entity engaged in the business of supplying agricultural products to the government of Abu Dhabi, a constituent emirate of U.A.E.
2. Joel Gutierrez is the chief executive officer and a principal of [Seller].
3. On March 7, 2008, the [Buyer] entered into a contract with [Seller] under which [Seller] would deliver 5,000 tons of compressed hay at a price of $315.00 per metric ton for a total price of $ 1,575,000.00. Compl. Ex. 5 [DE # 1-5]. After some problems arose with delivery of this initial amount, the parties modified the contract on July 17, 2008 to require 16,400 tons at the same price of $315.00 per metric ton for a total price of $5,166,00.00. Compl. Ex. 6 [DE # 1-6].
4. As part of the contract, [Buyer] paid a down payment of $787,500.00 to [Seller], which [Buyer] financed with a loan form a local bank. Compl. ¶ 15 [DE # 1].
5. [Buyer] had also entered into a contract with Abu Dhabi to sell the hay it received from [Seller] for approximately $415.00 per ton. The expected net profit per ton after expenses was $100.00 per ton for a total net profit of $1,640,00.00. Under this contract, Abu Dhabi required [Buyer] to procure a performance bond in the amount of $452,000.00. Post-Hearing Brief, at 2-3 [DE # 29].
B. Breach of Contract
6. [Buyer] never received any hay from [Seller] pursuant to the contract. Compl. ¶ 25 [DE # 1].
7. As a result, [Buyer] was forced to cancel the contract with Abu Dhabi, and Abu Dhabi has refused to release the $452,000.00 bond. Post-Hearing Brief, at 3 [DE # 29].
8. Moreover, in the years leading up to the instant contract, [Buyer] had routinely entered into contracts with Abu Dhabi for the sale of hay and expected to renew the contract with Abu Dhabi in subsequent years. However, since [Buyer] canceled its contract with Abu Dhabi in 2008, Abu Dhabi has refused to engage in hay business transactions with [Buyer]. Id.
9. Additionally, as a result of Defendant's breach, [Buyer] defaulted on the loan by which it procured the $787,500.00 down payment, and litigation is imminent. Id.
C. Fraudulent Inducement
10. On March 7, 2008, Samer Mustafa, the Executive Director of [Buyer], traveled to Jacksonville, Florida, where he met with Gutierrez to negotiate the contract. Compl. [DE # 1].
11. Mustafa credibly testified at trial and the Court finds that Gutierrez represented that [Seller] had actually shipped 200,000 tons of agricultural products in the past and that it currently had double compressed hay available for shipment. See also Post-Hearing Brief, at 6-7 [DE # 29].
12. Gutierrez also falsely represented that he owned land and warehouses of hay in Nebraska, that this hay would be shipped by train to a seaport, and that the hay would then be shipped by sea to [Buyer].
13. On July 17, 2008, at which point no hay had been delivered to [Buyer], Samer returned to Jacksonville, where Gutierrez told him that the hay was ready to be shipped to [Buyer] aboard a vessel, that this vessel had space for additional hay, and that the vessel also contained another quantity of hay to be delivered to another entity in U.A.E. These statements were also false.
14. The false statements by Gutierrez on behalf of [Seller] described in paragraphs eleven through thirteen were material to [Buyer's] decision to enter into the initial and modified contracts with [Seller].
15. [Buyer] relied on these false representations in entering into the initial and modified contracts with [Seller], making a down payment on the contracts, and entering into the resale contract with Abu Dhabi, for which it obtained the aforementioned performance bond. Id.
II. Conclusions of Law
A. Breach of Contract
16. The breach of contract claim is governed by the United Nations Convention on Contracts for the International Sale of Goods ("CISG") [1] because the United States, where [Seller] has its place of business, and U.A.E., where [Buyer] has its place of business, are both States party to the Convention. Compl. ¶ 26. See also MCC-Marble Ceramic Ctr., Inc. v. Ceramica Nuova d'Agostino, S.P.A., 144 F.3d 1384 (11th Cir. 1998).
14. Article seventy-four of the CISG provides as follows:
Damages for breach of contract by one party consist of a sum equal to the loss, including loss of profit, suffered by the other party as a consequence of the breach. Such damages may not exceed the loss which the party in breach foresaw or ought to have foreseen at the time of the conclusion of the contract, in the light of the facts and matters of which he then knew or ought to have known, as a possible consequence of the breach of the contract.
CISG, art. 74.
17. But for [Seller's] breach, [Buyer] would have paid the remaining purchase price of $4,378,500.00. This cost was avoided by virtue of the breach.
18. But for [Seller's] breach, [Buyer] would have earned approximately $6,806,000.00 from reselling the hay to Abu Dhabi, reflecting a net profit of $100.00 per ton. [Seller] ought to have foreseen this loss at the time of the conclusion of the contract.
19. Under article seventy-four of the CISG, [Buyer] is entitled to recover the lost proceeds of the resale to Abu Dhabi less the purchase price [Buyer] never had to pay ($6,806,000.00-$4,378,500.00), which is equal to $2,427,500.00, as this is the position [Buyer] would have been in had the contract been performed as expected. This figure can also be expressed as [Buyer's] total expected profit ($100/ton * 16,400 tons) of $1,640,000.00 plus the down payment of $787,500.00 it did not recover for a total of $2,427,500.00.
20. The loss of the performance bond was also a harm that [Seller] ought to have foreseen as a possible consequence of its breach of the contract at the time of the conclusion of the contract.
21. Therefore, under article seventy-four of the CISG, [Buyer] is also entitled to recover for the loss of the performance bond, amounting to $452,000.00, which is an additional loss [Buyer] suffered as a consequence of [Seller's] breach.
22. The damages awarded under the contract would be the same under the CISG or Florida law.
B. Fraudulent Inducement
23. A federal court with diversity jurisdiction over a case applies the conflict-of-laws rules of the jurisdiction in which it sits. Klaxon Co. v. Stentor Electric Mfg. Co., Inc., 313 U.S. 487, 61 S. Ct. 1020, 85 L. Ed. 1477 (1941).
24. Florida applies the "most significant relationship" test to determine the law that applies to tort claims. Garcia v. Pub. Health Trust of Dade Cnty., 841 F.2d 1062, 1065 (11th Cir. 1988).
25. Under the most significant relationship test, Florida law applies to the fraudulent inducement claim because, inter alia, a substantial part of the inducement took place in Florida and Defendants reside, are domiciled, and conduct business in Florida. See, e.g., Auto Internet Marketing, Inc. v. Targus Info. Corp., 2008 U.S. Dist. LEXIS 98595, 2008 WL 5138302, *3-4 (M.D. Fla. Dec. 5, 2008).
26. Under Florida law, "fraudulent inducement is an independent tort in that it requires proof of facts separate and distinct from the breach of contract." HTP, Ltd. v. Lineas Aereas Costarricenses, S.A., 685 So.2d 1238, 1239 (Fla. 1996). Therefore, "[a] right of action on a contract and for fraud in inducing plaintiff to enter into such contract may exist at the same time . . . ." Id. (internal citation omitted).
27. "An agent is personally liable for damage caused to third persons by an agent's fraud or false representations, even though the agent is acting in behalf of his or her employer, and even though the agent receives no benefit from the transaction." 37 Am. Jur. 2d. Fraud and Deceit § 315. Therefore, both [Seller] and Gutierrez are liable for fraudulent inducement resulting from Gutierrez's misrepresentations to Mustafa.
28. As a result of the fraudulent inducement, [Buyer] is entitled to "the difference between the value represented and the value receiver," which "allows the recovery of lost profits if they can be proven with reasonable certainty." Id. at § 385. "[A] defrauded party may also recover any additional damages that are a natural and proximate consequent of the defendant's misrepresentations." Id.
29. Under Florida law, a defendant may be held liable for punitive damages when the trier of fact finds intentional misconduct or gross negligence by a standard of clear and convincing evidence. Fla. Stat. § 768.72(2) (2011). "'Intentional misconduct' means that the defendant had actual knowledge of the wrongfulness of the conduct and the high probability that injury or damage to the claimant would result and, despite that knowledge, intentionally pursued that course of conduct, resulting in injury or damage." Id. "'Gross negligence' means that the defendant's conduct was so reckless or wanting in care that it constituted a conscious disregard or indifference to the life, safety, or rights of persons exposed to such conduct." Id.
30. The Court finds that [buyer] is entitled to punitive damages of $500,000.00 based on its claim for fraudulent inducement against Gutierrez and [Seller].
III. Conclusion
In sum, [Seller] and Gutierrez are jointly and severally liable to [Buyer] for a total of $3,379,500.00, comprised of $2,879,500.00 in expectancy and consequential damages and $500,000.00 in punitive damages.
Based on the foregoing, it is hereby ORDERED and ADJUDGED that:
[Buyer] is entitled to judgment in the amount of $3,379,500.00 against [Seller] and Joel Gutierrez.
Pursuant to Federal Rule of Civil Procedure 58(a), the Court will enter final judgment by separate order.
DONE and SIGNED in Chambers at West Palm Beach, Florida, this 7th day of November, 2011.}}
Source
Original text in English:
- available at the University of Pace Law website, http://cisgw3.law.pace.edu}}